UK Power Station
Strategic procurement underpins effective
project delivery
A major European power generator, currently
providing power to the national grid in the UK, was in the process
of procuring a contractor to deliver a major new Combined Cycle
Power Plant. However, the UK market for power construction was
overheated, resulting in fewer contractors being prepared to submit
prices for erecting the new power stations.
Contractors were concerned with the balance of risk in
traditional lump sum power station erection contract documents.
Market research also confirmed that many contracting companies did
not believe that current power station contract terms allowed an
equitable share of the risks.
EC Harris was appointed to provide procurement advice and to
devise a procurement strategy that would balance risk more fairly
between the client and contractor. This was to protect the client
against spiralling budgets and also allow the contractor scope to
reach an equitable agreement on time and cost.
Creating solutions
EC Harris considered a number of options for the procurement
strategy, moving away from the standard tendering procedure and
avoiding simple Lump Sum Turnkey Contracts which the market would
not sustain.
EC Harris also found that the client had a number of concerns
which needed to be addressed before they could embark on the
construction process. These challenges included incomplete design
of the works, the procurement of major plant was not finalised and
the client still required cost security.
To determine the optimum procurement strategy EC Harris
considered the whole life cycle of the built asset to ensure the
method adopted provided the client with the ultimate long-term
outcome. Often the temptation is to select the perceived lowest
cost solution, which over the lifecycle of the project can
potentially be more costly in both real and environmental
terms.
The procurement route decided upon was a Reimbursable Target
Cost contract, priced by the tenderers on the basis of the NEC 3
Standard Form Contract, Option C.
Adding value
EC Harris designed a procurement strategy that led to contract
terms that satisfied the client’s and the contractor’s needs. This
enabled the procurement of the new Combined Cycle Power Plant to
proceed. The solution delivered significantly increased the
tendering pool and ensured a broader range of tenders were
received. This provided the client with a competitive environment
and as a result they successfully appointed a contractor.
As a direct result of the EC Harris tender appraisal the second
highest bidder reduced their price substantially, by over £60
million. This ensured that the difference between the two lowest
tenders was only around 1%, allowing the client to choose the
successful contractor on the basis of quality and performance.
By involving EC Harris in the early stages of the project the
client has found that the best lifecycle cost also provides the
best build cost. Quite often there is a qualitative decision to be
made as to whether capital expenditure costs today should be
sacrificed for future operational savings. This decision could only
be made by the client once fully informed on the lifecycle cost
options.
The project is now underway and EC Harris is working with the
client to deliver the Combined Cycle Power Plant within budget
providing project controls, project costing and commercial
management.
Download the UK
Power Station article [84kb]